Glasgiven delivers an inspirational campus

Leading the project across demolition, civils works, construction, fitting out and M&E installation, the Banbridge contractor has achieved BREEAM Excellent for the build…

Shimna Integrated College in Newcastle is a £28m design-and-build project, funded through the UK government’s Fresh Start Programme supporting integrated education, and providing accommodation for 620 pupils.

Glasgiven Contracts Ltd was appointed as main contractor for the 10,000sqm post-primary school, with the build commencing in 2023 and delivered in four phases to maintain uninterrupted operation of the existing adjacent school during construction.

Phase one involved the construction of a new two- and three-storey school incorporating 43 classrooms, science labs, a manufacturing and technology department, resource, preparation and ancillary rooms, and sixth-form study. Also included were a library, multi-purpose hall, canteen and kitchen, fitness suite, reception and administration offices, while external works included a maintenance building, glasshouse, external play areas, access space, parking and landscaping.

 

Phase two demolished the old school building, phase three saw construction of the sports hall and changing facilities, and phase four completed the project with final site works and parking.

Glasgiven appointed and managed all sub-contractors and suppliers, including specialist contractors, to undertake demolition, civils works, construction works, fitting out, and installation of mechanical and electrical services.

Undertaking RIBA Stage 4 Technical Design, Glasgiven’s remit included enabling works, site clearance and groundworks, building retaining structures, substructures and foundations and waterproofing. Works also entailed superstructures, envelope and facades, roofs, lift installations and utilities infrastructure and services diversions.

The contractor led internal fitting out and finishes, joinery carpentry, partitions, screens, signage, furniture and specialist equipment, and integration of ICT and AV systems. External works encompassed drainage, landscaping, upgrading access onto a public road, and courts and play areas.

Among construction challenges was the site, with diversion of existing watercourses and significant retaining wall structures required to build the new split-level school into a hill.

Glasgiven installed temporary diversions of natural watercourses around both the existing and new buildings with temporary drainage to divert and control run off during construction until the final permanent solution was installed.

With the retaining wall structure running the whole length of the building including a semi-basement lower level, works were sequenced and carefully coordinated to maintain safety when adjacent to the live school environment.

Glasgiven adopted a proactive approach to weather risk, introducing a robust stud partition system for the internal walls to provide programme certainty, ensure consistent quality in the finishes and provide future flexibility in internal layout. Precast systems were also used to accelerate the programme and avoid any impact from weather.

Working in a live school environment required meticulous planning, with Glasgiven holding daily coordination meetings with school representatives and negotiating separate site access with adjacent landowners to ensure separation of construction traffic.

Temporary routes with barriers and solid hoardings were created to segregate pupils from the construction site, while maintaining existing exit routes with directional signage. Live utility services were managed by Glasgiven with each utility company to ensure existing supplies were uninterrupted, with crossover periods programmed during school holidays to avoid disruption.

The contractor’s community liaison officer was employed for the project duration to manage community interfaces.

To meet the requirements for BREEAM Excellent, Glasgiven maintained ‘inert’ demolition material on site for use in the new construction and siteworks. The BREEAM process involved regular meetings and workshops to review actions required to meet the sustainability targets.

Amanda Mason, Bid Manager, says, “Glasgiven has a long-standing connection with the school, having constructed part of the original school building many years ago. This legacy continues with the new school development, located in the area where Glasgiven was originally founded.

“Glasgiven successfully led the team in delivering a modern, state-of-the-art learning environment that will inspire future generations of students, set between the stunning backdrop of the Mourne Mountains and the sea.”

A family-owned and operated business with a firm commitment to safe, high-quality, client-focused project delivery, Glasgiven is based at new headquarters in Banbridge, Co Down with a regional office in Dublin.