Representing the largest integrated transport hub on the island of Ireland, the new £340m Belfast Grand Central Station is also among the single biggest investments of any kind in Northern Ireland.
Farrans Sacyr Joint Venture (JV) was appointed as lead contractor for the main construction project, tasked with creating a new multi-modal transport hub to replace the existing Europa and Great Victoria Street bus and rail stations.
The contractor’s successful history of working on important infrastructure projects also includes delivering Edinburgh Trams to Newhaven for City of Edinburgh Council.
Belfast Grand Central Station is part of the eight-hectare Weavers Cross development, a transport-led regeneration project which includes mixed-use development proposals and is aiming to attract 50,000 new jobs and £1bn investment into the city.
Client Translink anticipates Belfast Grand Central Station will serve 20 million journeys per year by 2040.
Site preparation works were completed by GRAHAM Civil Engineering over 18 months and included site clearance, utility diversions, ecology surveys, ground remediation, watercourse and drainage activities.
Commencing in February 2022, Farrans Sacyr JV led construction of the new interchange, which comprises a station concourse, 26 bus stands, eight railway platforms, bus maintenance and parking, a bus access bridge, cycle and taxi provision and car parking.
Also entailed in the project were the new Saltwater Public Square; public realm, highway and infrastructure improvements; temporary structures for bus operations during construction; and temporary site construction compounds.
Duane McCreadie, Project Director, said, “Farrans Sacyr JV was contracted to construct the main works elements on the Belfast Grand Central Station project, which included the main building, platform construction and site-wide civils including upgrading the local road network.
“The project was constructed in one of the most notable, globally-challenging periods we can remember, including Covid, the Ukraine War, very high inflation and the construction skills gap.
“Delivering this project on time and on budget is a testament that a genuinely collaborative culture can ensure client and contractors work together when faced with significant challenges to generate the best project outcomes.”
Indeed, such was the success of its collaboration, the project saw Farrans Sacyr JV recognised as Team of the Year at the Irish News Workplace and Employment Awards 2024.
A local, trusted supply chain
Over the course of five months up to September 2022, more than 1,400 piles were placed to support the main station superstructure.
A complex build then followed, involving coordination of multiple sub-contractors and suppliers including more than 80 local companies working on the project.
“We used a local, trusted supply chain, with most of the products and supply chain sourced within 50 miles of the site, where this was possible from a capacity or specification point of view,” said Duane.
“We also used a lot of off-site manufacturing including fully-complete manholes and platform retaining walls, and tried to ensure our products were environmentally friendly, for example using recyclable piling mat, which was significant for the size of the building.”

Sustainability informed the overall project, with environmental sustainability a focus of both the construction process and initiatives incorporated throughout the station.
Community outreach activities, meanwhile, included a careers’ open day for 75 female students from five city schools on the construction site to inspire the next generation.
Phase one of the project opened in September 2024, with public realm works surrounding the new station set to continue through 2025.
“Belfast Grand Central Station provided a refreshing approach to construction,” said Duane. “We were part of a collaborative team with our client and other project partners. Challenges were faced together to ensure the best project decisions were always at the heart of what we did.
“The project was handed over on time, on budget, to a high standard of quality and with one million hours worked without a reportable accident.”
John Glass, Director of Infrastructure and Projects at Translink, said, “Farrans-Sacyr JV delivered the Grand Central Station successfully, as a direct result of the importance they placed upon a collaborative working culture.”
Project team…
Client: Translink
Main contractor: Farrans Sacyr JV
Architect: John McAslan + Partners
Design & structural engineer: Arup
M&E contractor: Dowds Group
Rail infrastructure contractor: Babcock